ISA Interchange

Welcome to the official blog of the International Society of Automation (ISA).

This blog covers numerous topics on industrial automation such as operations & management, continuous & batch processing, connectivity, manufacturing & machine control, and Industry 4.0.

The material and information contained on this website is for general information purposes only. ISA blog posts may be authored by ISA staff and guest authors from the automation community. Views and opinions expressed by a guest author are solely their own, and do not necessarily represent those of ISA. Posts made by guest authors have been subject to peer review.

All Posts

Always Design in Spare Capacity to Allow for Industrial Plant Expansion

 

The following tip is from the ISA book by Greg McMillan and Hunter Vegas titled 101 Tips for a Successful Automation Career, inspired by the ISA Mentor Program. This is Tip #19. and was written by Hunter.

 

Over my career I cannot think of a single time when I regretted running spare cables or oversizing field junction boxes. However, I can think of too many instances where I ran out of room and/or capacity much sooner than I had expected, and wished I had run MORE spares.

 

Concept: The incremental purchase cost of a 36 pair cable over a 24 pair cable is practically negligible when compared with the labor cost of running either cable. Install spare wire capacity whenever possible, or at least plan for future expansion when sizing junction boxes, cable trays, and control system I/O.

Details: During system design, always run spare cable, oversize the field junction boxes, and buy extra I/O cards. Ideally, the cost of this spare capacity can be worked into the project cost during the estimating phase so the money will be available when the project is approved. Even if the spare capacity was not included in the original budget, the additional cost of adding the extra capacity is usually low enough that it can be incorporated with no significant impact on the budget. If the project budget is so tight that larger cables or spare capacity cannot be installed, at least PLAN for future additions. Install slightly bigger field junction boxes and cable trays so that more cables can be added later. Oversize conduits, and leave a draw string in them so wires can be pulled in on future projects. Leave blank spaces in the I/O cabinets so I/O racks can be added later, or at least leave space in the room so I/O cabinets can be installed in a future project.

This concept is particularly true when running fiber optic cable. The labor to run a 6 fiber, 12 fiber, or 24 fiber cable is essentially the same and the material cost difference is low. Running a cable with less than 12 fibers is pointless, and if expansion is even slightly possible, run a 24 fiber cable.

 

Watch-Outs: Always ask about future expansion plans during the design phase of an automation project. By knowing how the ultimate system might appear, you can make minor design changes that will make future growth much less costly and difficult. If the system will double in size, you can lay out the I/O cabinets, power supplies, etc. in such a way that they can be easily upgraded in the future without burdening the current project significantly.

Exceptions: Occasionally an automation project involves a machine or a process that is so mature that future expansion is unlikely. This is not a common occurrence, but if this situation applies, clearly the cost of adding spare capacity would not be justified.

Insight: Project managers hate adding spare capacity after the project has been approved because they consider it “scope creep” and not part of the project. Plants adore spare capacity because it allows the execution of process improvement projects at a much reduced cost. In the long run, the company certainly saves money, but the project manager is not nearly as concerned with the long run as the execution of his or her project. If the spare capacity is included in the original project estimates, then all parties win. The project manager is happy because the project scope has not changed, and the plant and company are happy because they can expand in the future at a much reduced cost.

Rule of Thumb: A common rule of thumb for most systems is to add at least 25 percent spare capacity to the original design. Depending upon the future plans of the plant, a higher percentage might be justified. Adding less than that figure is usually not advisable unless the plant and/or process are mature and unlikely to change.

 

About the Author
Gregory K. McMillan, CAP, is a retired Senior Fellow from Solutia/Monsanto where he worked in engineering technology on process control improvement. Greg was also an affiliate professor for Washington University in Saint Louis. Greg is an ISA Fellow and received the ISA Kermit Fischer Environmental Award for pH control in 1991, the Control magazine Engineer of the Year award for the process industry in 1994, was inducted into the Control magazine Process Automation Hall of Fame in 2001, was honored by InTech magazine in 2003 as one of the most influential innovators in automation, and received the ISA Life Achievement Award in 2010. Greg is the author of numerous books on process control, including Advances in Reactor Measurement and Control and Essentials of Modern Measurements and Final Elements in the Process Industry. Greg has been the monthly "Control Talk" columnist for Control magazine since 2002. Presently, Greg is a part time modeling and control consultant in Technology for Process Simulation for Emerson Automation Solutions specializing in the use of the virtual plant for exploring new opportunities. He spends most of his time writing, teaching and leading the ISA Mentor Program he founded in 2011.

 

Connect with Greg
LinkedIn

 

Hunter Vegas, P.E., holds a B.S.E.E. degree from Tulane University and an M.B.A. from Wake Forest University. His job titles have included instrument engineer, production engineer, instrumentation group leader, principal automation engineer, and unit production manager. In 2001, he joined Avid Solutions, Inc., as an engineering manager and lead project engineer, where he works today. Hunter has executed nearly 2,000 instrumentation and control projects over his career, with budgets ranging from a few thousand to millions of dollars. He is proficient in field instrumentation sizing and selection, safety interlock design, electrical design, advanced control strategy, and numerous control system hardware and software platforms.

 

Connect with Hunter
LinkedIn

 

Greg McMillan
Greg McMillan
Gregory K. McMillan, CAP, is a retired Senior Fellow from Solutia/Monsanto where he worked in engineering technology on process control improvement. Greg was also an affiliate professor for Washington University in Saint Louis. Greg is an ISA Fellow and received the ISA Kermit Fischer Environmental Award for pH control in 1991, the Control magazine Engineer of the Year award for the process industry in 1994, was inducted into the Control magazine Process Automation Hall of Fame in 2001, was honored by InTech magazine in 2003 as one of the most influential innovators in automation, and received the ISA Life Achievement Award in 2010. Greg is the author of numerous books on process control, including "New Directions in Bioprocess Modeling and Control Second Edition 2020" and "Advanced pH Measurement and Control Fourth Edition 2023." Greg has been the monthly "Control Talk" columnist for Control magazine since 2002. Greg has recently retired as a part-time modeling and control consultant in Technology for Process Simulation for Emerson Automation Solutions specializing in the use of the digital twin for exploring new opportunities. Greg received the ISA Mentoring Excellence Award in 2020 and the ISA Standards Achievement Award in 2023.

Related Posts

3 Ways Industry 4.0 Can Upgrade Industrial Water Treatment Methods

Industrial water treatment methods must evolve to remain relevant and efficient. Many decision-makers hav...
Emily Newton Mar 12, 2024 7:38:26 PM

ISA Business Academy: A Mini-MBA For Automation Industry Leaders

The ISA Business Academy is a 10-week fully digital program beginning 28 March for both current and aspir...
Ashley Ragan Mar 11, 2024 10:08:24 AM

How Automation Is Transforming the Recycling Industry

Modern recycling industry professionals are increasingly interested in how automation could boost their o...
Ellie Gabel Mar 8, 2024 8:00:00 AM