ISA Interchange

Welcome to the official blog of the International Society of Automation (ISA).

This blog covers numerous topics on industrial automation such as operations & management, continuous & batch processing, connectivity, manufacturing & machine control, and Industry 4.0.

The material and information contained on this website is for general information purposes only. ISA blog posts may be authored by ISA staff and guest authors from the automation community. Views and opinions expressed by a guest author are solely their own, and do not necessarily represent those of ISA. Posts made by guest authors have been subject to peer review.

All Posts

How a Sequenced Changeover Approach for a Plant Upgrade Minimizes Downtime

This blog post was written by Marc Hunter, a global consultant with Rockwell Automation. 

With the help of a consulting engineering firm and system integrator, a major Midwest steel producer successfully upgraded the main blast furnace and stove control system with no interruption in overall blast furnace or stove control system operations. The challenge was to create a transition plan and minimal-risk implementation (with no impact to production or product quality) with zero production outages, improved technology with future expansion capabilities, improved process controls, enhanced operator interface, significant improvements to system reliability, and stringent budgetary guidelines.

The determination to upgrade this system came from numerous factors. The input/output components were obsolete, making it more and more difficult to stock parts and find replacement units. The legacy system was UNIX based, so many members of the current on-site engineering staff were not familiar with it. Because the plant had to maintain continual operations levels, as well as to retain overall control strategies and functional knowledge of system operations, a custom system was devised to make the transition gradual and “self-teaching.” This protocol was termed the system transition execution plan (STEP).

The STEP protocol allows for a gradual transition and an opportunity for self-teaching along the way. At the heart of the concept is a strategy developed around a core principle of zero downtime during the changeover. Essentially, a building block operation was created in which each control input/output on the old system was upgraded with parallel monitoring of performance values and system readouts. The changeover of the control strategies occurred only when each new component was functioning properly and the signals were in line with the existing monitored values. This was then integrated loop by loop into the new process local area network.

All of that was performed in a phased approach, section by section, over 18 months. The plant benefited, because through the gradual weaning from the legacy system, the plant’s operational and maintenance personnel could become thoroughly familiar with the new hardware and software systems.

 

New control screens were designed for a similar look and feel to the legacy screens, which allowed process control engineers to implement the changeover more smoothly and with a minimal learning curve.

Another crucial dimension of migrating and integrating new controls for this project was to solicit and receive “constant operator input.” The nuances of the entire manufacturing process are both critical to future plant operations and are second nature for the operators who have worked in the plant for the past 30 years. So all the things operators do throughout the process are captured and programmed into the new automation. Integrator engineers worked with seasoned blast furnace operators on every step in the process. As a result, the new system was entirely designed and installed working on site at the steel mill with plant personnel.

This project required verification and movement of nearly 2,000 I/O points, installation of new workstations, network communication upgrades, development of more than 60 human-machine interface screens with built-in diagnostics and alarms, extensive programmable logic controller programming, system functional documentation development and drawing approval, historian upgrades, and on-site training.

One reason the automation vendor felt the process worked so smoothly was there were very few bugs. When bugs did come up, the systemized process facilitated working with operational and technical support to fix them immediately.

Using the STEP approach, not only was the manufacturing process minimally affected, but the plant realized significant financial savings, both in operational expense and total project cost. Because this project happened in steps, it could be charged as a maintenance expense and billed monthly. The plant did not need to seek approval for a major capital expenditure.

The plant now has the technology to further enhance its automation strategies and drive flexibility and productivity in ways that were not available with the legacy automation platform. Engineering confirmed its complete satisfaction with the outcome of this major project and is looking to repeating the process on a second blast furnace when demand for steel picks up.

 

About the Author
Marc Hunter is a global consultant with Rockwell Automation. Previously, he was vice president at Synergy Systems, Inc. He has more than 20 years of experience in the automation industry and specializes in marketing, systems engineering, and project management.
Connect with Marc:

48x48-linkedin

 

A version of this article also was published at InTech magazine

 


Related Posts

Checking In With Mimo, ISA's Large Language Model Trained on ISA Content

Over the summer of 2024, the International Society of Automation (ISA) announced a large language model (...
Kara Phelps Nov 15, 2024 7:00:00 AM

Ask the Automation Pros: The Use of Artificial Intelligence in Process Control

The following discussion is part of an occasional series, "Ask the Automation Pros," authored by Greg McM...
Greg McMillan Nov 12, 2024 4:30:00 PM

Protecting Electrical Terminal Blocks From Tampering

Electrical terminal blocks are a common sight in the automation world. Usually mounted on DIN rail in ind...
Anna Goncharova Nov 8, 2024 10:30:00 AM