ISA Interchange

Welcome to the official blog of the International Society of Automation (ISA).

This blog covers numerous topics on industrial automation such as operations & management, continuous & batch processing, connectivity, manufacturing & machine control, and Industry 4.0.

The material and information contained on this website is for general information purposes only. ISA blog posts may be authored by ISA staff and guest authors from the automation community. Views and opinions expressed by a guest author are solely their own, and do not necessarily represent those of ISA. Posts made by guest authors have been subject to peer review.

All Posts

Project Management Is More Than a Disruption: It Is Real Work

This is an excerpt from the March/April 2014 issue of InTech magazine by Brent Karickhoff,  operations manager at Transdyn, Inc. To read the full article, please see the link at the bottom of this post.

Modern control systems are sophisticated assemblies with varied state-of-the-art technologies. Implementing these systems requires a team of technically gifted technicians and engineers who welcome the challenge of taking the often disparate pieces of a complex system and merging them into an integrated control system.electrical switch panel

Although these teams can resolve high-tech matters, they do not always adapt to the less technical requirements of project management. The project manager's focus on controlling schedule, budget, and scope is often viewed as a disruption to the technical, or "real work," of designing, programming, and deploying the system.

The truth is, consistent project success requires strong technical skills and good project management practices. The project manager should apply a focused management process that addresses the critical needs of good project management practices while minimizing the disruption to the technical work being performed.

The following list of key components are the basis of a sound system integration project management plan.

1. Project goals definition.The project team must clearly define the project's functional, schedule, and financial goals, and determine a method for confirming that these goals have been achieved. The time expended defining goals pays significant dividends later by keeping the team focused only on those tasks required for success on the project.

2. Project schedule. Albert Einstein once said, "The only reason for time is so that everything does not happen at once." Every project is made up of a list of tasks that must be done before the project is complete. The project schedule distributes the list of project tasks over the time available. This can be a challenge in the systems integration arena, where there are significant external dependencies beyond the control of the project team. However, even a fundamental list of properly sequenced tasks with planned durations can be invaluable when concentrating the project team's efforts on the immediate tasks at hand.

The project schedule is a "living document," regularly updated to capture project progress. It plays a critical role in the project manager's ability to document and mitigate the impact of any delays.

3. Project risk. Once the goals and the schedule are defined, the next step is to identify all threats to achieving the established goals. This includes developing a list of risk items and a mitigation strategy for each. The most overlooked step is a quantitative evaluation of the potential impact of each risk item to the success of the project. It should include an estimate, in terms of time and cost, of the worst-case scenario for each item.

Project risk analysis should drive the extent to which time and resources are expended to mitigate. Too often, effort is expended to address a high-profile or emotionally charged risk item that is perceived as a considerable danger to the project. However, if accurately quantified, it may be determined that the actual threat is less damaging than the disruption caused by the mitigation effort. In these cases, it is best to take no action and simply deal with the situation when and if it occurs. The project risk list is also a "living document" to be reviewed and maintained throughout the project.

Once the defining tasks are complete and technical work has commenced, the project manager must shift to controlling the project within the established parameters.

To read the full article on project management, click here.

About the Author
Brent KarickhoffBrent Karickhoff, PMP, is operations manager at Transdyn, Inc., based in Duluth, Ga. Transdyn is a certified member of the Control System Integrators Association

Connect with Brent:
48x48-linkedin


Related Posts

IoT Solutions World Congress: Why Barcelona is the Place to Be in May

A century ago, automation solutions arrived to transform manual industrial tasks. This century, the digit...
Renee Bassett Apr 2, 2024 7:00:00 AM

3 Ways Industry 4.0 Can Upgrade Industrial Water Treatment Methods

Industrial water treatment methods must evolve to remain relevant and efficient. Many decision-makers hav...
Emily Newton Mar 12, 2024 7:38:26 PM

ISA Business Academy: A Mini-MBA For Automation Industry Leaders

The ISA Business Academy is a 10-week fully digital program beginning 28 March for both current and aspir...
Ashley Ragan Mar 11, 2024 10:08:24 AM